Tank Farm Foundations at Khazaen: From Excavation to Concrete Placement

اقرأ بالعربية

At an oil and lubricant factory in Khazaen Economic City, the foundations for the tank farm were part of Light Sky’s civil works subcontract. The octagonal bases made it especially important to verify the geometry before concrete placement. The sequence starts with setting out and preparing the ground.

Confirm the layout and prepare the formation

Use the approved layout and survey reference points to confirm the position, footprint and formation level of each foundation. Excavation, levelling and compaction were part of the scope at Khazaen. Mark any discrepancies between the site and the drawings for review before the next activity goes ahead.

Agree when the prepared ground is to be inspected and which records are required. Where the drawings call for a lean concrete blinding layer, check the formation before covering it.

Check the geometry, reinforcement and embedded items

For an octagonal base, confirm that the formwork faces, centre lines, dimensions and levels correspond to the approved drawings. Check the reinforcement position, supports and concrete cover against those drawings. Also verify the locations of any sleeves, anchors or other embedded items shown in the approved details.

A documented inspection before placement gives the civil and installation teams a chance to resolve discrepancies while the formwork and reinforcement are still accessible. Use the inspection and testing requirements specified for the project.

Define the entire work sequence in the RFQ

Include the current drawing revision and the available site and survey information. Specify whether excavation, disposal, backfill, compaction, blinding, formwork, reinforcement and concrete placement are included. Make clear who supplies each item and who is responsible for any embedded components associated with the tanks.

State which inspection records, material submittals, tests and as-built information the contractor must provide. A complete scope helps bidders price the same work and helps the project team plan handovers between work stages.